TARGET FIELD BUDGET:

Original Ballpark Project Budget:
Source:
Infrastructure $90 Million Hennepin County $90 Million
Ballpark $390 Million Hennepin County $260 Million
Minnesota Twins $130 Million
Total Budget $480 Million $480 Million
AmendedĀ Ballpark Project Budget:
Source:
Infrastructure $120 Million Hennepin County $90 Million
Minnesota Twins $20 Million
Target Corp $4.5 Million
MNDOT $3.5 Million
MBA $2 Million
Ballpark $435 Million Hennepin County $260 Million
Minnesota Twins $175 Million
Total Budget $555 Million $555 Million